Case Studies

Not a Repair. A Reinvention and Modernization of a 1,200 Ton Chiller

Refrigerant-Cooled to Air-Cooled VFD & Controls Retrofit

Download
Project Case Study

Not a Repair.
A Reinvention.

How a trusted customer relationship and cross-discipline field engineering turned a catastrophic VFD failure into a more flexible, visible, and serviceable 1,200-ton chiller.

Project Progress Highlights Completed MCS controls cabinet, air-cooled VFD, and custom bus bars on a 1,200-ton centrifugal chiller
1,200Tons of cooling capacity
$35KApproximate customer savings
680 lb.VFD positioned in constrained access
30-40%Potential faster future execution
Project at a glance

A Failed Drive Created a Larger Decision

The central question

Should the customer restore the same proprietary configuration or use the failure as an opportunity to build a better long-term solution?

Equipment1,200-ton centrifugal chiller
FailureCatastrophic failure of the refrigerant-cooled OEM VFD
SolutionAir-cooled VFD, MCS controls, custom power distribution, sensors, and BMS integration
Primary goalsRestore capacity, improve visibility, reduce proprietary dependence, and strengthen future serviceability
The challenge

The Familiar Repair Would Have Restored the Same Limitations

The chiller's refrigerant-cooled VFD had failed severely. Replacing it through the original manufacturer was possible, but the repair would have returned the machine to the same proprietary architecture, expensive components, limited communication, and potential parts lead-time concerns.

The facility also needed better visibility. The existing controls provided limited information to the building automation system. Operators could start the machine, but they did not have the alarm detail and operating data needed to see a developing problem quickly.

Interior of the failed OEM chiller VFD showing its power electronics and control boards
The annotated view shows the power electronics and control boards inside the failed OEM VFD that triggered the larger modernization decision.
Original repair path

Return to the OEM Configuration

Replace the failed power module and proprietary components, restoring the chiller largely as it had operated before the failure.

Engineered path selected

Modernize the Drive and Controls

Install an air-cooled VFD and modern controls platform that could improve visibility, BMS integration, serviceability, and future support options.

Trust made the engineered option possible.

Our technicians had built a relationship with the customer over time and already understood the facility's equipment and controls challenges. That history allowed us to present both paths honestly and recommend what we believed was in the facility's best interest. The customer trusted our technicians to pursue the less familiar option because the recommendation came from an established understanding of their operation, not simply the failure in front of us.

The engineered solution

A Modern Controls Strategy Built Around the Existing Machine

The underlying chiller remained a viable asset. Rather than discard the entire machine or return it to the same controls limitations, our technicians designed the new drive and controls strategy around its mechanical, refrigeration, electrical, and operational requirements.

Air-Cooled VFD

Selected for the compressor's electrical and torque requirements, physical cabinet fit, and available conditioned airflow.

MCS Controls Platform

Configured to control the chiller and give operators access to useful alarms, status, and operating points.

New Sensors and Wiring

Proprietary communication wiring and incompatible sensors were replaced for the new control architecture.

Custom Power Distribution

Bus bars were fabricated, bent, drilled, and fitted to connect the new equipment cleanly.

Cabinet and Airflow Changes

Existing fans, terminal blocks, and usable cabinet components were repurposed where appropriate.

BMS Integration

Modbus communication gave the customer's controls provider better access to chiller data and alarms.

BeforeChiller electrical cabinets after the failed OEM VFD and original components were removed
The original cabinet spaces after demolition and before the new drive and controls architecture was installed.
Near CompletionCompleted MCS chiller controls panel, air-cooled VFD, and custom bus bar installation
The completed modernization includes the MCS operator interface, air-cooled VFD, and custom-fabricated power connections.
Planning and execution

The Work Was Sequenced Before the First Component Was Removed

The value was not in adding complexity. It was in managing the complexity well. Compatible tasks were planned to move forward together so our technicians could use recovery and vacuum time productively while protecting the quality of the final installation.

01 · RECOVERProtect the refrigeration circuit

Refrigerant was recovered while compatible sensor and wiring work moved forward.

02 · REMOVEClear the old architecture

The failed drive, obsolete controls, refrigerant piping, and incompatible wiring were removed.

03 · REBUILDFabricate around the machine

Power distribution, cabinet support, airflow, sensors, and control wiring were reconfigured.

04 · INTEGRATECommission the full system

The drive, chiller controls, safeties, and BMS communication were tested together.

Refrigerant vessel suspended from a digital scale during refrigerant removal for a 1,200-ton chiller modernization
Before modernization began, our technicians removed and weighed the refrigerant as part of the carefully planned chiller preparation process.
Retrofit in Progress Electrical cabinets, reactor, wiring, and power connections during the 1,200-ton chiller retrofit
Cabinet demolition, reactor placement, heavy power connections, fan reuse, and wiring changes progressed as coordinated parts of one retrofit plan.
Hand-fitted copper bus bars connecting the three-phase electrical components inside the existing chiller cabinet
The annotated view shows the hand-fitted copper bus bars and three-phase connections built around the existing cabinet.
Craftsmanship in the details

Functional Was the Minimum Standard

An early bus bar approach could have operated safely, but it did not meet our technicians' standard for the finished installation. New four-inch bus bar material was sourced, bent, drilled, and hand-fitted to create a cleaner result.

The cabinet was treated the same way. Existing components were reused when they supported the new design, but the wiring, airflow, mounting, and layout were rebuilt to function as one intentional system.

Why the details mattered

Future technicians need to be able to open the cabinet, understand the work, and service it confidently. A clean installation supports long-term reliability and reflects ownership of the finished result.

The 680-pound constraint

The VFD Was Going Into Position One Time

The new VFD weighed approximately 680 pounds. It had to move through narrow access between chillers, and the space did not provide a practical overhead rigging option.

Our technicians measured the cabinet, mounting points, wall support, and equipment path in advance. They developed a custom lifting approach and installed the support structure before the move began. Once the drive was lifted, it needed to land exactly where planned.

Annotated mechanical-room view showing approximately five feet between the VFD cabinet location and the adjacent chiller
With approximately five feet between the chillers, our technicians had one opportunity to position the 680-pound VFD correctly.
Documented impact

The Customer Gained More Than a Working Chiller

The retrofit restored the customer's critical cooling capacity while addressing limitations that a return to the original configuration would have left in place.

Approximately $35,000 saved

The engineered modernization cost approximately $35,000 less than the proposed OEM repair path.

Shorter anticipated lead time

The selected components provided a more practical path to restoring the machine than waiting for the original power module.

Better operational visibility

Operators gained access to alarms, operating points, status information, and remote monitoring capabilities.

Simplified BMS communication

Modbus integration gave the facility's controls provider access to meaningful chiller information.

Improved serviceability

The modern platform reduced dependence on proprietary boards and created more future support options.

New organizational capability

Our technicians now have a proven approach that can make a similar future retrofit an estimated 30 to 40 percent faster.

Original proprietary OEM chiller display compared with the modern MCS controls interface offering more operating data, improved diagnostics, and BMS integration
The side-by-side comparison shows the transition from the original OEM display to an MCS interface with greater operating visibility, diagnostic access, and BMS integration.
What the project proved

Better Options Come From Better Questions

This modernization required refrigeration knowledge, electrical calculations, controls integration, fitting, fabrication, planning, and collaboration. It also required our technicians to challenge the assumption that the machine had to return to the same proprietary solution.

The People Behind the Capability Josh W., Lead Service Technician at Oklahoma Chiller, smiling while seated on top of a chiller
Josh W., Lead Service Technician, represents the field experience, curiosity, and pride in craftsmanship behind complex work like this.
Evaluate the whole asset

A failed component does not automatically mean the original configuration remains the best answer.

Plan across disciplines

Mechanical, refrigeration, electrical, structural, controls, and BMS decisions must support one another.

Capture what was learned

The first successful retrofit becomes a repeatable capability that can improve future speed and customer value.

Project spotlight video

Watch the Modernization Come Together

See the demolition, custom fabrication, controls work, VFD placement, and final commissioning from the project.

Watch on YouTube
Repair, retrofit, or replace?

Give Your Facility More Than One Option

When a critical chiller component fails, the familiar repair is not always the only responsible path. Oklahoma Chiller can help you evaluate the machine, compare realistic options, and choose the solution that best supports your facility.

This article was prepared by the engineering, service, and technical experts at Oklahoma Chiller, supporting commercial and industrial facilities across Oklahoma and surrounding states.